Generating Unit Outage Report for 20-05-2019

A. Planned Outages
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1RAPS-ARAJASTHANNPC1100Subject to regulatory clearance . Unit is to be decommissioned.09-10-200422:58-
2Badarpur TPSDELHINTPC2100Order of NGT for Environmental protection, unit is to be decommissioned.24-09-201519:29-
3Badarpur TPSDELHINTPC3100Order of NGT for Environmental protection, unit is to be decommissioned.09-10-201501:00-
4Badarpur TPSDELHINTPC1100Order of NGT for Environmental protection, unit is to be decommissioned.30-10-201515:30-
5Bairasiul HPSHPNHPC360For renovation and Modernisation of the plant15-10-201809:1105-06-2019
6Bairasiul HPSHPNHPC260For renovation and Modernisation of the plant15-10-201810:0231-08-2019
7Bairasiul HPSHPNHPC160For renovation and Modernisation of the plant15-10-201810:1405-06-2019
8Badarpur TPSDELHINTPC4210Order of NGT for Environmental protection, unit is to be decommissioned.15-10-201818:05-
9Badarpur TPSDELHINTPC5210Order of NGT for Environmental protection, unit is to be decommissioned.15-10-201820:03-
10Auraiya GPSUPNTPC6109.30Reserve Shutdown Non-availibilty of gas30-11-201805:47-
11Auraiya GPSUPNTPC4111.19Reserve Shutdown 05-01-201910:42-
12Auraiya GPSUPNTPC5109.30Reserve Shutdown 08-01-201905:54-
13Auraiya GPSUPNTPC1111.19Reserve Shutdown 11-01-201910:06-
14Auraiya GPSUPNTPC2111.19Reserve Shutdown 12-01-201909:53-
15Dehar HPSHPBBMB1165Capital Maintenance28-01-201906:1521-05-2019
16Auraiya GPSUPNTPC3111.19Reserve Shutdown 11-02-201920:45-
17Pong HPSHPBBMB266Renovation and Modernization.14-02-201908:0031-05-2019
18Faridabad GPSHARYANANTPC2137.75Non-availability of cheap gas.01-03-201922:39-
19Faridabad GPSHARYANANTPC3156Non availability of gas.27-03-201921:17-
20Faridabad GPSHARYANANTPC1137.75Non availability of gas.27-03-201921:36-
21Bhakra-L HPSHPBBMB3108Renovation and Modernisation of unit(capacity enhancement from 108 to 126 MW)01-04-201909:2009-12-2019
22Singrauli STPSUPNTPC1200Annual maintenance 02-04-201922:3122-05-2019
23Bhakra-L HPSHPBBMB4108Runner modification and Annual Maintenance.04-04-201900:0031-05-2019
24ISTPP (Jhajjar)HARYANANTPC3500Annual maintenance 08-04-201900:00-
25Koteshwar HPSUTTRAKHANDTHDC1100Annual maintenance .09-04-201910:0021-05-2019
26Tanda TPSUPNTPC2110Annual overhauling.25-04-201900:3524-05-2019
27Dadri GPSUPNTPC4130.19Reserve Shutdown Module changeover27-04-201922:28-
28Dulhasti HPSJKNHPC3130S/D for turbine inspection miscellaneous05-05-201900:00-
29Dadri-I TPSUPNTPC1210Reserve Shutdown 18-05-201900:18-
 Sub Total(CS)  3922.05 
  State Sector (SS)
1Paricha TPSUPUPRVUNL1110R & M Work02-07-201617:3031-05-2019
2Guru Gobind Singh TPS (Ropar)PUNJABPSEB1210Unit under Shutdown. Life cycle completed.31-05-201707:15-
3Guru Nanak Dev TPS (Bhatinda)PUNJABPSEB2110Unit under Shutdown. Life cycle completed.22-06-201720:32-
4Guru Nanak Dev TPS (Bhatinda)PUNJABPSEB3110Unit under Shutdown. Life cycle completed.22-09-201701:02-
5Guru Nanak Dev TPS (Bhatinda)PUNJABPSEB1110Unit under Shutdown. Life cycle completed.27-09-201708:40-
6Guru Nanak Dev TPS (Bhatinda)PUNJABPSEB4110Unit under Shutdown. Life cycle completed.27-09-201708:40-
7Guru Gobind Singh TPS (Ropar)PUNJABPSEB2210Unit under Shutdown. Life cycle completed.25-12-201710:00-
8Guru Gobind Singh TPS (Ropar)PUNJABPSEB4210Reserve Shutdown 11-10-201813:10-
9Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB1210Reserve Shutdown 03-12-201822:50-
10Baglihar (IPP) HPSJKPDD JK3150Capital Maintenance 19-12-201818:00-
11Guru Gobind Singh TPS (Ropar)PUNJABPSEB3210Reserve Shutdown 30-12-201817:45-
12Panipat TPSHARYANAHPGCL5210Reserve Shutdown 04-01-201911:14-
13Panipat TPSHARYANAHPGCL6210Reserve Shutdown 04-01-201920:46-
14Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB4250Reserve Shutdown 21-03-201918:38-
15RGTPP( Khedar)HARYANAHPGCL1600Reserve Shutdown 31-03-201919:43-
16Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB2210Reserve Shutdown 15-04-201921:54-
17Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB3250Reserve Shutdown 15-04-201922:48-
18Guru Gobind Singh TPS (Ropar)PUNJABPSEB5210Reserve Shutdown 17-04-201910:10-
19Suratgarh TPS RAJASTHANRRVUNL2250Reserve Shutdown 01-05-201913:09-
20Chhabra TPSRAJASTHANRRVUNL4250Annual maintenance 08-05-201900:07-
21Panipat TPSHARYANAHPGCL7250Reserve Shutdown 10-05-201919:03-
22RGTPP( Khedar)HARYANAHPGCL2600Reserve Shutdown 10-05-201919:17-
23Guru Gobind Singh TPS (Ropar)PUNJABPSEB6210Reserve Shutdown 19-05-201920:40-
 Sub Total(SS) 5250 
Total Planned Outage (CS+SS): 9172.05

B. Forced Outages
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1Barsingsar (IPP) LTPSRAJASTHANNLC2125Manually hand tripped due to major overhaul12-04-201900:17-
2Kishanganga HEPJKNHPC3110Problem in cooling water system23-04-201913:46-
 Sub Total(CS) 235 
  State Sector (SS)
1Giral (IPP) LTPSRAJASTHANRRVUNL1125Bed materials leakage.11-07-201408:20-
2Giral (IPP) LTPSRAJASTHANRRVUNL2125Boiler tube leakage 27-01-201615:27-
3Obra TPS UPUPRVUNL12200Drum level high.24-09-201817:26-
4Kalisindh TPSRAJASTHANRRVUNL2600Tripped due to oil leakage in Y phase buchholz relay of GT-1 04-04-201914:01-
5Obra TPS UPUPRVUNL13200Boiler tube leakage Turbine governor system problem.14-04-201913:01-
6Suratgarh TPS RAJASTHANRRVUNL1250Tripped due generator earth fault15-04-201901:03-
7Paricha TPSUPUPRVUNL5250Boiler tube leakage 09-05-201903:27-
8Rajwest (IPP) LTPSRAJASTHANRRVUNL6135BED MATERIAL LEAKAGE11-05-201910:30-
9Harduaganj-C TPSUPUPRVUNL7105Tripped due to fire at Unit No:7 as informed by UPSLDC.15-05-201901:16-
10Talwandi Sabo TPSPUNJABPSEB3660Boiler tube leakage 17-05-201918:00-
11Lalitpur TPSUPLPGCL2660Boiler tube leakage 19-05-201914:45-
12Kalisindh TPSRAJASTHANRRVUNL1600Boiler tube leakage 20-05-201900:35-
13Kota TPSRAJASTHANRRVUNL5210Boiler tube leakage 20-05-201923:30-
 Sub Total(SS)4120 
Total Forced Outage (CS+SS): 4355

Regional Generation Outage Summary (MW)
Central SectorState SectorRegional Total Outage(MW)
PlannedForcedTotal(CS)PlannedForcedTotal(SS)
3922.052354157.0552504120937013527.05

C. Generating Units Revived during last day which were out before 20-05-19
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageRevival
DateTimeDateTime
  Central Sector (CS)
1TEHRI HPSUTTRAKHANDTHDC3250For Annual Maintenance work.25-04-201908:0020-05-201913:45
2Dadri GPSUPNTPC6154.51Reserve Shutdown Module changeover27-04-201922:5420-05-201923:15
3Dadri GPSUPNTPC3130.19Reserve Shutdown Module changeover27-04-201922:5720-05-201918:13
4Dadri-I TPSUPNTPC2210Reserve Shutdown Less Demand.10-05-201923:4820-05-201922:51
5Anta GPSRAJASTHANNTPC388.71Reserve Shutdown 13-05-201919:2420-05-201919:03
 Sub Total(CS) 833.41 
  State Sector (SS)
1Bara PPGCL TPSUPJaypee2660Generator Transformer protection operated 22-02-201912:4120-05-201922:52
2Suratgarh TPS RAJASTHANRRVUNL5250Reserve Shutdown 03-05-201919:1020-05-201919:18
3Suratgarh TPS RAJASTHANRRVUNL6250Reserve Shutdown 05-05-201923:2620-05-201920:44
4Rajwest (IPP) LTPSRAJASTHANRRVUNL1135Boiler tube leakage 16-05-201917:4220-05-201903:13
5Jhajjar-CLP (IPP) TPSHARYANAHPGCL2660Reserve Shutdown due to less demand.17-05-201923:0320-05-201913:30
 Sub Total(SS) 1955 
Total (CS+SS): 2788.41

D. Short Duration Outages during the day
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageRevival
DateTimeDateTime
  Central Sector (CS)
--No Outages--
 Sub Total(CS) 0 
  State Sector (SS)
--No Outages--
 Sub Total(SS) 0 
Total (CS+SS): 0

E. Outages due to Low Demand
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1Auraiya GPSUPNTPC6109.30Reserve Shutdown Non-availibilty of gas30-11-201805:47-
2Auraiya GPSUPNTPC4111.19Reserve Shutdown 05-01-201910:42-
3Auraiya GPSUPNTPC5109.30Reserve Shutdown 08-01-201905:54-
4Auraiya GPSUPNTPC1111.19Reserve Shutdown 11-01-201910:06-
5Auraiya GPSUPNTPC2111.19Reserve Shutdown 12-01-201909:53-
6Auraiya GPSUPNTPC3111.19Reserve Shutdown 11-02-201920:45-
7Dadri GPSUPNTPC4130.19Reserve Shutdown Module changeover27-04-201922:28-
8Dadri-I TPSUPNTPC1210Reserve Shutdown 18-05-201900:18-
 Sub Total(CS) 1003.55 
  State Sector (SS)
1Guru Gobind Singh TPS (Ropar)PUNJABPSEB4210Reserve Shutdown 11-10-201813:10-
2Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB1210Reserve Shutdown 03-12-201822:50-
3Guru Gobind Singh TPS (Ropar)PUNJABPSEB3210Reserve Shutdown 30-12-201817:45-
4Panipat TPSHARYANAHPGCL5210Reserve Shutdown 04-01-201911:14-
5Panipat TPSHARYANAHPGCL6210Reserve Shutdown 04-01-201920:46-
6Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB4250Reserve Shutdown 21-03-201918:38-
7RGTPP( Khedar)HARYANAHPGCL1600Reserve Shutdown 31-03-201919:43-
8Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB2210Reserve Shutdown 15-04-201921:54-
9Guru Hargobind Singh TPS (Lehra Mohabbat)PUNJABPSEB3250Reserve Shutdown 15-04-201922:48-
10Guru Gobind Singh TPS (Ropar)PUNJABPSEB5210Reserve Shutdown 17-04-201910:10-
11Suratgarh TPS RAJASTHANRRVUNL2250Reserve Shutdown 01-05-201913:09-
12Panipat TPSHARYANAHPGCL7250Reserve Shutdown 10-05-201919:03-
13RGTPP( Khedar)HARYANAHPGCL2600Reserve Shutdown 10-05-201919:17-
14Guru Gobind Singh TPS (Ropar)PUNJABPSEB6210Reserve Shutdown 19-05-201920:40-
 Sub Total(S S) 3880 
Total Low Demand Outage (CS+SS): 4883.55