Select Date Home
Transmission Elements Outage Report for 20-02-2018

A. Details of Transmission Elements under Planned Outage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalExpected Date of RevivalReason / Remarks
DateTimeDateTime
1Meerut - MogaLine765 kVPGCIL20-02-201808:3020-02-201819:28-Construction of new element ---- Erection of 04 nos. 7CC Towers, 04 nos. peaks and 06nos. Beams and Reactor Firewall no.1 (adjoining toexisting 765kV Meerut Line Reactor) of 765kV Bikaner-II Bay under construction at Moga S/S by Powergrid.
2Anta RS - Phagi - 2Line765 kVRRVPNL20-02-201811:3820-02-201823:45-Synchronization of spare reactor
3Allahabad Rewa Road(400kV) - ObraLine400 kVUPPTCL23-01-201810:03**20-02-2018Diverson of Line--- 1. for diversion of line due to infringement with railway siding of Meza Urja Nigam Ltd. at Meja TPS ( Work by UPPTCL loc. 467 to 475) .2. completion of diversion of line due to DFCC at Bhadraumarganj ( Work by UPPTCL between loc. 467 to 475)
4Bikaner (RVPNL) - Sikar (PG) - 1Line400 kVRRVPNL30-01-201811:38**30-01-2018General maintenance.....Final testing of CSD Relays ofMAIN CB & TIE CB of LineReactor (Non Switchable) atSikar S/s by Powergrid.
5Jhakri(SJVNL)-Rampur(SJVNL) -1Line400 kVPGCIL06-02-201808:55**28-02-2018....Preparation/Revival of Injection Point for HV Testing of GIS Bus Bar by at Rampur end by SJVNL.
6Dadri(NTPC)-Maharanibagh(PG)Line400 kVPGCIL14-02-201818:20**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
7Ballabgarh-MaharanibaghLine400 kVPGCIL14-02-201818:21**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
8Allahabad(PG)-Singrauli(NTPC) 1Line400 kVPGCIL15-02-201809:1620-02-201818:55-Diverson of Line.....Diversion of lines by Powergrid ( on deposit work) for Meza Urza Nigam LTD railway siding work at Allahabad.
9Agra(PG)-Agra(UP) 1Line400 kVPGCIL16-02-201810:48**20-02-2018General maintenance....."Retrofitting of existing 400kV Lines and Integration of SCADA with HVDC Control Room: It will be total new commissioning as all control & Power cables are need to be laid and changed a. Laying of new cables b. Termination of cables c. Green lining d. C&P testing and greenlining e. Commissioning & Charging (Line- 2), at AGRA HVDC" by Powergrid.
10Aligarh - PankiLine400 kVUPPTCL20-02-201807:5220-02-201819:36-.....For Replacementof damaged jumpers,tightening ofjumpers, lopping &chopping of treebranches and routinetesting by UPPTCL
11Nallagarh(PG)-Rampur(SJVNL)-2Line400 kVPGCIL20-02-201809:0920-02-201815:26-General maintenance.... Replacement of Insulated Driving Rods in GIS Disconnectors by SJVNL.
12Bhiwani(PGCIL)-Mohindergarh(Adani)-1Line400 kVAPL20-02-201809:1020-02-201817:31-......Bay EquipmentsMaintenanceActivity &Calibration ofMetering CTs by Adani.
13Bikaner (RVPNL) - Sikar (PG) - 1Line400 kVRRVPNL20-02-201810:3320-02-201819:12-.....Final testing of CSD Relays ofMAIN CB & TIE CB of LineReactor (Non Switchable) atSikar S/s by Powergrid.
14Muradnagar 315 MVA ICT 2ICT400/220 kVUPPTCL03-01-201810:52**21-02-2018Replacement of transformer..For Replacement/ augmentation of this 315 MVA ICT 2 with 500 MVA ICT 2 ( As a capacity enhancement at this substation) by UPPTCL.
15Maharanibagh 315 MVA ICT 1ICT400/220 kVPGCIL14-02-201817:48**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
16Maharanibagh 500 MVA ICT 4ICT400/220 kVPGCIL14-02-201817:49**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
17Maharanibagh 500 MVA ICT 3ICT400/220 kVPGCIL14-02-201817:49**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
18Amritsar 315 MVA ICT 2ICT400/220 kVPGCIL20-02-201810:1020-02-201817:47-General maintenance...For AMP Works by Powergrid.
19Merta 50 MVAR (400kV) B/Reactor 1Bus Reactor400 kVRRVPNL23-06-201709:01**21-02-2018Construction of new element --- for dismantling this 50 MVAR Bus Reactor(this reactor shall be shifted to 400kv Bhilwara) and replacing/commissioning with new TEBA make 125 MVAR Bus Reactor at Merta .
20400 kV Tie CB ( 411 ) of ( Agra ckt-1 & ICT-3 ) at Sikar (PG)BAY/CB400 kVPGCIL03-02-201810:13**28-02-2018.....Erection of Structure/Equipment/Al. Bus pipe under augmentation scheme of 500 MVA ICT -3 & 02 no. of 220 kV Line bays at Sikar(PG).
21400 kV Tie BAY / CB ( 408 ) of ( ICT-4 & ICT-2 ) at Ballabgarh (PG)BAY/CB400 kVPGCIL03-02-201810:13**02-03-2018.....Retro fitment of Existing Old M&G Circuit Breaker with New Siemens CB
22Mau 400 kV Bus 2BUS400 kVUPPTCL04-02-201810:30**22-02-2018General maintenance--- replacement of partially damaged conductor in 400kv Bus 2 at Kasara Mau.
23Maharanibagh 400 kV Bus 2BUS400 kVPGCIL14-02-201818:21**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
24Maharanibagh 400 kV Bus 1BUS400 kVPGCIL14-02-201818:21**25-02-2018General maintenance......(i) Rectification of Y and B Ph , B3 Module at 400 kV GIS of 315 MVA ICT 2 bay (Bay no 404) by Powergrid. (ii) For above rectification work ,Sf6 gas shall be evacuated from 400 kV Bus I & II adjoining to Y & B phase B-3 module. So 400 kV BUS I & II shall remain out of service till reassembling
25400 kV Main CB / Bay ( 406 ) of 315 MVA ICT-2 at Bhinmal (PG) BAY/CB400 kVPGCIL20-02-201809:55**23-02-2018.....For AMP Works by Powergrid.
26Nallagarh 400 kV Bus 2BUS400 kVPGCIL20-02-201810:1920-02-201816:44-General maintenance.....FOR AMP WORKS by Powergrid.
27Gangwal-JagadhriLine220 kVBBMB10-02-201811:47**25-02-2018General maintenance.......For modification of line between span no. 182 - 186/CJ & 202 - 203/CJ & 159 -160/CJ due to 4 laning of Panchkula - Yamunanagar section (Highway NH -73) Deposit work of NHAI.
28Debari(RVPNL)-RAPS A(NPC)Line220 kVRRVPNL20-02-201809:0120-02-201821:09-....For Destringing and Stringing of Earth Wireat location no. 401-411 by RRVPNL.
29Hamirpur (HPSEB)-Hamirpur(PG) Line220 kVPGCIL20-02-201809:3820-02-201817:31-General maintenance....For line & Bay AMPworks by Powergrid.
30Hisar(PG)-Isharwal(HVPNL) 2Line220 kVHVPNL20-02-201811:3320-02-201819:07-For replacement of Y & B-Ph LA of the line.
31FSC of Pampore-2 at KishnprFSC220 kVPGCIL30-10-201212:00**NALine length has reduced after LILO work completion
32FSC of Pampore-1 at KishnprFSC220 kVPGCIL30-10-201212:00**NALine length has reduced after LILO work completion
33Dhampur(UP)-Kalagarh(Uttrakhand)Line132 kVUPPTCL20-02-201807:5220-02-201818:35-General maintenance.....For Line maintenanceworks by UPPTCL.
*-Line still under outage     NA - Not Available

B. Details of Transmission Elements under Forced Outage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalExpected Date of RevivalReason / Remarks
DateTimeDateTime
1Agra - Biswanath Cherialli line -1 Line800 kV HVDCPGCIL20-02-201809:33**NATo control power flow of Agra-Gwalior I and II
2Agra - Biswanath Cherialli line -2Line800 kV HVDCPGCIL20-02-201810:13**NATo control power flow of Agra-Gwalior I and II
3Vindhyachal HVDC BtB Block 2HVDV Station500 kV HVDCPGCIL26-11-201714:55**28-02-2018Differential protection operated.
4Bawana-Mundka 1Line400 kVDTL14-05-201709:03**28-02-2018Fire below 400kV tower no. 116, in the line
5Bawana-Mundka 2Line400 kVDTL14-05-201709:50**28-02-2018Manually Opened due to Fire below 400kV tower no. 116, in the line leading to Insulator damage and Tower bend
6Dhanonda-Jhajjar CLP-2Line400 kVHVPNL14-06-201715:00**28-02-2018Tower No. 12 to 17 collapsed
7Dhanonda-Jhajjar CLP-1Line400 kVHVPNL14-06-201715:00**28-02-2018Tower No. 12 to 17 collapsed.
8Akal (RVPNL)-Ramgarh 400 (RVPNL) 1Line400 kVRRVPNL11-12-201721:18**28-02-2018Tower collapse from tower no. 92 to 95.Conductor theft as reported by RRVPNL
9Akal (RVPNL)-Ramgarh 400 (RVPNL) 2Line400 kVRRVPNL29-12-201715:16**28-02-2018Tower collapse from tower no. 92 to 95.Conductor theft as reported by RRVPNL
10Mainpuri(PG)-Paricha(UPPTCL) -1Line400 kVUPPTCL20-02-201800:5020-02-201801:40-Tripped on Y-G fault,57.9KM from Mainpuri end
11Bareilly II (PG) - Kashipur (UTT) - 2Line400 kVPGCIL20-02-201811:3520-02-201814:58-For replacement of burnt y-phase female blade and fixed contact of isolator 414-89A of tie breaker CB-414
12Kashipur (UTT) - Roorkee (PG) - 2Line400 kVPGCIL20-02-201816:1720-02-201817:49-For repairing isolator No. 414-89B (TIE Breaker Isolator)
13Lucknow-Lucknow II 1Line400 kVPGCIL20-02-201819:4520-02-201819:53-Phase to earth faultpHASE TO EARTH FAULT
14Mainpuri(PG)-Paricha(UPPTCL) -1Line400 kVUPPTCL20-02-201821:5620-02-201823:28-Tripped on Y-G fault, 14.9KM from Mainpuri end.
15Rajpura (400kV) 500 MVA ICT 3 ICT400/220 kVPGCIL18-06-201707:02**NABuchholz relay operated / Detail inspection work.
16Dhuri(400) 500 MVA ICT 2ICT400/220 kVPSTCL19-08-201710:47**NABus bar protection operatedBuchholz relay operated / will replace by new.
17Maharanibagh 500 MVA ICT 2ICT400/220 kVPGCIL01-09-201716:19**28-02-2018Bus bar protection operateddue to flashover in ICT-II Gas chamber
18Bawana 315 MVA ICT 2ICT400/220 kVDTL30-11-201720:20**NA400kV side R-ph bushing damaged.
19Ramgarh 400 (RVPNL) 500 MVA ICT 3ICT400/220 kVRRVPNL22-12-201712:58**NAS/D for filling of SF6 gas in 220kV bay CB.
20Wagoora 50 MVAR B/RBus Reactor400 kVPGCIL22-04-201518:56**NATaken out due to low voltage.
21FACT at BLB in Knp-BLB LineFACTS400 kVPGCIL02-07-201610:20**NAY-Phase current imbalance
22FSC (40%) of Fatehpur-I at MainpurI(PG)FSC400 kVPGCIL02-03-201707:38**NAB-Ph spark gas cable fail
23FSC (40%) of Fatehpur-II at MainpurI(PG)FSC400 kVPGCIL07-05-201713:13**NAB-ph Capacitor unbalance
24FSC ( 50% ) of Koteshwar Pool -2 at Meerut (PG)FSC400 kVPGCIL14-07-201719:22**NAFire in Y-ph unit
25FSC of Balia-I at LucknowFSC400 kVPGCIL29-11-201713:30**NAHot Spot at Isolatot
26Kurukshetra(PG) 400 kV Bus 2 (BB2)BUS400 kVPGCIL02-02-201811:57**25-02-2018Due to flashover in GIS disconnector/ earth-switch, 400KV BUS-2 bus-bar protn. operated at Kurukshetra.
27400 kV Main BAY/CB ( 402-52 ) of Ballabhgarh 1 at Bamnauli (DTL)BAY/CB400 kVDTL20-02-201817:0020-02-201817:44-To attend Low SF6 pressure.
28Allahabad(PG)-Naini Railway( Railway) 2Line220 kVRLY01-01-201813:25**NAE. S/D availed by Railways for CVT testing work at Naini end.
29220KV_Kota(PG)-Kota Th(RRVPN)-2Line220 kVRRVPNL19-02-201803:08**NAPhase to earth faultCVT damaged at KTPS end.
30Duni(RVPNL)-Kota(PG)Line220 kVRRVPNL19-02-201822:2020-02-201808:50-Line opened for power regulation of 220KV KTPS-Kota(PG) Line
31Kota Th-Sakatpura 3Line220 kVRRVPNL20-02-201801:0220-02-201801:29-Tripped on R-G fault, 12.2KM from Kota end
32Lalton Kalan(PSEB)-Ludhiana(PG)Line220 kVPSTCL20-02-201809:0720-02-201819:06-Hot point is detected on Y-phase CT clamp on line isolator side at lalton
33Duni(RVPNL)-Kota(PG)Line220 kVRRVPNL20-02-201812:05**NADue to power regulation
34Baghpat(PG)-Muradnagar New(UP)Line220 kVUPPTCL20-02-201814:1420-02-201818:59-To attend Red Hot at R- Phase , at Tower Loc. 122 of the line
*-Line still under outage     NA - Not Available

C. Details of Transmission Elements Opened manually due to High Voltage:-
S.NoElement NameTypeVoltage LevelOwnerOutageRevivalRemarks
DateTimeDateTime
1Meerut - MogaLine765 kVPGCIL19-02-201820:5520-02-201806:50 
2Agra-FatehpurLine765 kVPGCIL20-02-201801:0520-02-201806:40 
3Meerut - MogaLine765 kVPGCIL20-02-201820:50**** 
4Agra-Fatehpur 2Line765 kVPGCIL20-02-201821:17**** 
5Agra(PG)-Auraiya(NTPC) 1Line400 kVPGCIL15-02-201813:1520-02-201809:42 
6Agra-Bhiwadi 2Line400 kVPGCIL17-02-201813:0520-02-201807:49 
7Agra-Sikar 1Line400 kVPGCIL19-02-201802:5520-02-201809:36 
8Fatehpur-Mainpuri 2Line400 kVPGCIL19-02-201813:1920-02-201807:53 
9Ballabgarh-Mainpuri 1Line400 kVPGCIL19-02-201813:2020-02-201807:52 
10Ratangarh (RVPNL) - Sikar (PG) - 1Line400 kVPGCIL19-02-201820:0420-02-201806:17 
11Jodhpur II-Merta 1Line400 kVRRVPNL19-02-201820:0520-02-201806:15 
12Nallagarh(PG)-Parbati Pool(PG)Line400 kVPKTCL19-02-201820:0820-02-201807:46 
13Nallagarh-Patiala 1Line400 kVPGCIL19-02-201820:0820-02-201805:55 
14Amritsar-Parb-pol 1Line400 kVPGCIL19-02-201820:1020-02-201807:45 
15Bhiwadi-Neemrana 1Line400 kVPGCIL19-02-201820:2020-02-201807:20 
16Bhiwadi-HisarLine400 kVPGCIL19-02-201820:2120-02-201807:30 
17Nallagarh(PG)-Rampur(SJVNL) -1Line400 kVPGCIL19-02-201820:2420-02-201805:50 
18Jhakri-Panchkula 2Line400 kVPGCIL19-02-201820:4120-02-201805:27 
19Jhakri(SJVNL)-Karchamwangtoo(JP) 2Line400 kVJPHYDRO19-02-201820:4420-02-201805:22 
20Merta-RatangarhLine400 kVRRVPNL19-02-201820:4520-02-201806:14 
21Chamera pool-Jalandhar 1Line400 kVPGCIL19-02-201821:3320-02-201805:46 
22Fatehabad-HisarLine400 kVPGCIL19-02-201821:3420-02-201807:39 
23Chamera I(NHPC)-Jalandhar(PG) 2Line400 kVPGCIL19-02-201821:3520-02-201805:52 
24Jalandhar-Kurukshetra(PG) 1Line400 kVPGCIL19-02-201821:3520-02-201807:24 
25Abdullapur(PG)-Kala Amb(PKATL) 1Line400 kVJPL19-02-201821:4420-02-201805:33 
26Kala Amb(PKATL)-Karchamwangtoo(HBPCL) 1Line400 kVJPL19-02-201821:4720-02-201805:27 
27Agra-Jaipur South-2Line400 kVPGCIL19-02-201822:0320-02-201806:32 
28Amritsar(PG)-Malerkotla(PG) 1Line400 kVNRSS31B20-02-201801:0720-02-201807:27 
29Makhu -Nakodar -1Line400 kVPSTCL20-02-201801:33**** 
30Agra-Sikar 1Line400 kVPGCIL20-02-201813:13**** 
31Agra-Bhiwadi 2Line400 kVPGCIL20-02-201817:53**** 
32Agra-Jaipur South-2Line400 kVPGCIL20-02-201817:57**** 
33Chamera pool-Jalandhar 1Line400 kVPGCIL20-02-201820:09**** 
34Amritsar-Parb-pol 1Line400 kVPGCIL20-02-201820:10**** 
35Nallagarh(PG)-Parbati Pool(PG)Line400 kVPKTCL20-02-201820:11**** 
36Chamera I(NHPC)-Jalandhar(PG) 2Line400 kVPGCIL20-02-201820:12**** 
37Jhakri-Panchkula 1Line400 kVPGCIL20-02-201820:13**** 
38Jhakri(SJVNL)-Karchamwangtoo(JP) 1Line400 kVJPHYDRO20-02-201820:16**** 
39Bhiwadi - Hisar 2Line400 kVPGCIL20-02-201820:38**** 
40Ratangarh (RVPNL) - Sikar (PG) - 1Line400 kVPGCIL20-02-201820:39**** 
41Fatehabad-Nuhiyawali 2Line400 kVHVPNL20-02-201820:40**** 
42Khedar-Nuhiyawali 2Line400 kVHVPNL20-02-201820:4020-02-201822:37 
43Bhiwadi-Neemrana 1Line400 kVPGCIL20-02-201820:40**** 
44Amritsar(PG)-Malerkotla(PG) 1Line400 kVNRSS31B20-02-201821:05**** 
45Abdullapur(PG)-Kala Amb(PKATL) 1Line400 kVJPL20-02-201821:10**** 
46Nallagarh-Patiala 2Line400 kVPGCIL20-02-201821:11**** 
47Kala Amb(PKATL)-Karchamwangtoo(HBPCL) 1Line400 kVJPL20-02-201821:14**** 
48Jalandhar-Kurukshetra(PG) 1Line400 kVPGCIL20-02-201821:15**** 
49Mandola(PG)-Narela(DTL) 1Line220 kVDTL20-02-201818:21**** 
** - Line shall be closed subject to voltage permissibility